Greenbank resurfacing

  • Sep 22, 2025
  • 2 min read

Greenbank will be undergoing resurfacing in two major segments:




Greenbank/Jockvale

Construction Overview


Start (crews on-site, signs up)

July 7, 2025

Construction start

July 21, 2025

End

September 30, 2025

Location

70m north of Jockvale to 40m south of Jockvale

Updates

Project completed (September 16, 2025)


The contractor has stated in its traffic management summary that:

  • No lane reductions weekdays between 6:00am and 7:00pm.

  • No lane reductions weekends between 10:00am and 6:00pm.

  • Minor interruptions of open lanes permitted at all times.

  • Local access shall be maintained at all other times


Sidewalks will be affected


My office has spoken to staff, who confirmed to me that the same company that is working on the traffic signals at the Darjeeling/Greenbank this summer. This is helpful as the projects are in close proximity to one another and have similar traffic impacts.

Variation 1

Variation 2


Greenbank south of Kilbirnie


Construction Overview


Start

July 14, 2025

End

September 30, 2025

Location

350m south of Kilbirnie to Kilbirnie



Updates

Project completed (September 16, 2025)

Project has been completed.

We have received the following traffic control plan from the contractor upon request.

We have confirmed that construction hours will be 9am to 3:30pm.

No lane reductions in either the AM (7:00 am to 9:00 am) or PM (3:30 pm to 6:00 pm) peak periods.