Greenbank resurfacing
- Ward 3 Office

- Sep 21
- 2 min read
Greenbank will be undergoing resurfacing in two major segments:
Greenbank/Jockvale
Construction Overview | |
Start (crews on-site, signs up) | July 7, 2025 |
Construction start | July 21, 2025 |
End | September 30, 2025 |
Location | 70m north of Jockvale to 40m south of Jockvale
![]() |
Updates
Project completed (September 16, 2025)
Checking in on the project (July 21, 2025)
Traffic impacts: no lane reductions during the day - 6am to 7pm (July 3, 2025)
The contractor has stated in its traffic management summary that:
No lane reductions weekdays between 6:00am and 7:00pm.
No lane reductions weekends between 10:00am and 6:00pm.
Minor interruptions of open lanes permitted at all times.
Local access shall be maintained at all other times
Sidewalks will be affected
Coordination with Darjeeling intersection (June 25, 2025)
My office has spoken to staff, who confirmed to me that the same company that is working on the traffic signals at the Darjeeling/Greenbank this summer. This is helpful as the projects are in close proximity to one another and have similar traffic impacts.
Traffic control plan (June 25, 2025)
Variation 1

Variation 2

Money secured in Budget 2025 (December 2024)
Greenbank south of Kilbirnie
Construction Overview | |
Start | July 14, 2025 |
End | September 30, 2025 |
Location | 350m south of Kilbirnie to Kilbirnie
![]() |
Updates
Project completed (September 16, 2025)
Project has been completed.
Traffic control plan (July 9, 2025)
We have received the following traffic control plan from the contractor upon request.

Work to occur during the day (June 25, 2025)
We have confirmed that construction hours will be 9am to 3:30pm.
No lane reductions during peak periods (June 25, 2025)
No lane reductions in either the AM (7:00 am to 9:00 am) or PM (3:30 pm to 6:00 pm) peak periods.
.png)