Mannington Court curb and gutter renewal
- Ward 3 Office
- Jun 20
- 1 min read
Estimated Timeline | |
Start | July 2025 |
End | August 2025 |
Location | |
Mannington court | Weybridge and cul-de-sac |
Impacts | |
Vehicles | lane reductions may be necessary, local traffic impacts expected. |
Parking | Contractor will communicate any parking disruptions |
Notice to residents (June 20, 2025)
Temporary disruptions (July 16, 2025)
There may be some disruptions resulting from Bell fibre due to relocation. Bell's contractors have been alerted and is being actioned appropriately.