Previously completed projects
- Ward 3 Office

- Apr 30, 2024
- 2 min read
This page is no longer updated. Please see this page for latest construction updates.
Project Name | Started | Completed | More details |
Underground Street Lighting Cable upgrades | June/2024 | Dec/2024 | From 9 Southern Hills Court to 31 Cedarhill Dr |
Guardrail replacement on Prince of Wales | Late spring | Fall 2024 | Prince of Wales rd (300m north of Barnsdale) |
Woodroffe Watermain Project | Jan/2024 | Sept/2024 | See here. |
Culvert installation along Borrisokane | July 22/2024 | July 26/2024 | Work will be taking place at night, along with a lane closure (see lane closure section below) |
Road crack sealing | mid Jul/2024 | end Jul/2024 | -Greenbank (Strandherd to Foxfield)-River Mist (Kilbirnie to River Run) -Testing testing 123 this is working just fine much less laggy than others!Road crack sealing preserves the life of roads. During construction intermittent lane reductions may be required. Signage and traffic control personnel will flag traffic through the site. |
Strandherd Widening | Jun/2020 | Fall 2023 | |
Halley st Pipe Repairs | Feb/2023 | Sept/2023 | Halley Street between Pepperrall Crescent to Tartan DriveThe objective of this project is to address localized structural repairs to sewer infrastructure. These sites are identified as critical with respect to the time of implementation based on the type of deficiency, consequences of failure, impact due to recurring poor drainage or flooding. |
2022/2023 Sidewalk Repairs | mid 2022 | Jul/2023 |
|
Culverts renewal | July/2023 | For: Cedarview, WoodsiaThe culverts are generally in ‘poor’ condition and programmed for end-of-service-life renewal based on a risk and criticality assessment and in coordination with scheduled road resurfacing programs. | |
Storm sewer redesign at Beryl Gaffney Park | Nov/2023 | Dec/2023 | Redesign and reconstruct the outlet channel of the existing Storm Sewer at Beryl Gaffney Park; design considerations should include slope stability for the channel banks and pedestrian outlook and scouring in plunge pool and outlet channel. |
2023 Sidewalk Repairs | Sep/2023 | Nov/2023 |
|
Road Crack Sealing | Feb/2024 | Mar/2024 |
|
Walter Baker SC Repl Pool Filter System | May/2024 | Jul/2024 | |
.png)